A41 Work Begins Today

Major new work starts on one of Hertfordshire's main roads today, the A41.

Resurfacing work, carried out by Eurovia on behalf of Hertfordshire County Council, will begin on the A41 from Bourne End to Tring tomorrow (9 June).

The £271,000 resurfacing scheme will take place in various phases until 18 June, weather permitting. 


"    Phase 1: A41 westbound off slip at Hemel Hempstead, up to and including the Stoney Lane/Upper Bourne End Lane roundabout, overnight (8pm-5am)for three nights from Tuesday 9 June to Thursday 11 June


"    Phase 2: Between the A41 westbound off slip at Bourne End and the A4251 roundabout.  The A41 will be closed overnight on Friday 12 June and the A4251 will be closed overnight on Monday 15 June.


"    Phase 3: A41 on/off slip roads eastbound and westbound at Chesham, Berkhamsted overnight on Tuesday 16 June.


"    Phase 4: A41 eastbound at interchange roundabout in Tring overnight on Wednesday 17 June.

Recently Played Tracks

On TV: 24 Reasons We Heart Christmas!

4pm - 6pm

Watch heart TV

  • Destiny's Child 8 Days Of Christmas

    16:34

    iTunes

  • East 17 Stay Another Day

    16:28

    iTunes

  • Bon Jovi Please Come Home For Christmas

    16:21

    iTunes

  • Wizzard I Wish It Could Be Christmas Everyday

    16:17

    iTunes

Heart VIP

Local

Autumn Weather

Find your local four day weather report here.

Listening To Radio Win With Heart

Make Heart the soundtrack to your day and you could be a winner with great prizes up for grabs throughout the day.

Shopping Our Advertisers

Find out more about some of the companies advertising on Heart Watford & Hemel Hemstead.

Follow Heart on Twitter